Transit: upstream provider maintenance (Equinix LD6, UK)
Scheduled Maintenance Report for Cloudhelix
Completed
The scheduled maintenance has been completed.
Posted May 01, 2020 - 04:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 30, 2020 - 22:00 BST
Scheduled
We have been notified by Centurylink that they will be carrying out essential network maintenance during this window.

The work is required to replace a damaged joint on a core fibre backbone cable.

During this time customers in this region may see some brief periods of intermittency and/or sub-optimal routing due to route reconvergence over alternate providers.

Should you have any questions or concerns, please reach out to Cloudhelix Support via support@cloudhelix.io or call +44 1273 987 920.
Posted Apr 14, 2020 - 11:56 BST
This scheduled maintenance affected: Backup & DR (Veeam Cloud Connect, Zerto) and Network (External Transit, Datacenter Interconnect, Public Peering).